  "format": "bwp-green-document",
  "version": 1,
  "tool": "landscape-change-order",
  "values": {
    "company": "Sample Landscape Co. (fictional)",
    "customer": "Jordan L. (fictional)",
    "property": "Willow Court / project WC-01 - fictional property reference",
    "reference": "WC-01 / change 01 against scope revision 0",
    "requested": "Fictional customer requests four additional plants within the same bed. Revised plant total: 22.",
    "effects": "Same 216 ft² bed and mulch quantity. Add four reviewed plants. Incremental labor: 4 person-hours x $32 = $128; materials $52; incremental cost $180.",
    "price": "Proposed and fictionally accepted increase: $240 before any applicable tax. $180 / 0.75 = $240 at a 25% target margin. Revised project price $2,309.34.",
    "timing": "Review supplier availability and production capacity. No changed installation date is confirmed in this example.",
    "pending": "Crew follows the original scope until the sample approval is recorded. Do not treat this document as a real authorization.",
    "decision": "Fictional status: accepted by Jordan L. under the sample project process. No actual signature or customer approval is captured by this tool.",
    "handoff": "Issue scope revision 1 and 22-plant schedule to the crew; mark revision 0 superseded. Keep the bed area and mulch assumptions unchanged."
  }
}